Best week I've had in 3 years, 14 panel swaps in 5 days in Fort Worth
So last week I had a builder call me about a 26 home subdivision going up in Fort Worth and every house needed a full panel swap plus 4 contacts and a motion. Normally that's a 3 week job but the framing crew was already gone so I could just run wire without tripping over anybody. Knocked out all 14 in 5 days, and the best part was the builder let me pick the routing so I zip tied everything before drywall instead of fishing after. What's your record for panels in a week and do you change your price when the house is still open?